MDOT Wiscasset Downtown Project update
Mon, 03/18/2019 - 4:30pm
According to Maine Department of Transportation, the following activities are planned in downtown Wiscasset, beginning March 31.
From March 31 to April 18, the contractor will be installing drainage and catch basins on Main Street from Water Street to just beyond the railroad tracks.
From March 31 to April 7, the electrical subcontractor will be installing street lights around the Railroad Avenue parking lot and installing foundations for street lights and pedestrian pedestals along Main Street.